PMU (November 26, 2013): The National
Government of the FSM transmitted a revised Settlement Offer to Weno road Contractor,
Pacific International, Inc. (PII) on November 26, 2013, proposing to rescind
the November 7, 2013 Notice of Termination and offering the Contractor
additional time and money to settle disputed claims raised by PII. PII has until Friday, December 6, 2013, to
accept the offer or to submit a counter offer to the FSM Program Management
Unit (PMU).
The
offer proposes to extend the Contractor’s performance time for 281 days past
the November 25, 2013, contract completion date and raises the total contract
price by $1,761,076.07. This amount
includes costs additional work as well as extended overhead. In addition,
the Government proposes to release retention of $412,411.75, provided the
Contractor uses the funds to increase manpower and to mobilize additional
machinery and plant deemed necessary to accelerate production.
In
consideration of the additional time and money to complete the contract work,
PII must provide the Government with an amended schedule and a plan to improve
its rate of progress. The Government’s
estimate is that it would take PII two years to complete the work unless PII
mobilized additional equipment and manpower resources. PII has indicated that it would need more
money than the remaining contract balance of $3,273,573 (as of the September
progress payment) to complete the work and that it would charge the Government
$7,770.21 daily overhead and profit rate after November 25, 2013 to remain on
the job. Assuming it would take PII two
more years to complete the job, that claim that would result in a $5,672,253 cost
overrun just for the Contractor to remain on Weno, for a total estimated
payment of $8,945,826.
The November 7, 2013,
Notice of Termination for Default follows repeated attempts by the Government
to request that PII take steps necessary to improve its progress. The Notice of Termination cited Section 1.44
of the Contract which provides: “If in
the opinion of the Contracting Officer, the Contractor falls behind the
approved schedule, the Contractor shall take steps necessary to improve its
progress, including those that may be required by the Contracting Officer,
without additional cost to the Government.”
In addition, the Section provides that the failure of the Contractor to
comply with these requirements shall be grounds for a determination by the
Contracting Officer that the Contractor is not prosecuting the work with
sufficient diligence to ensure completion within the time specified in the
Contract. The Contracting Officer has
determined that PII did not take steps necessary to improve progress. Section 1.56 of the Contract provides that
when the Contractor fails to prosecute the work and fails to complete the work
on time, written notice may terminate the right to proceed with the work.
For more information, call the PMU Office at 320-2080 or email fsmpio@mail.fm.
No comments:
Post a Comment